ARTC has committed to publishing the following Performance Indicators in line with the undertaking:
Number | Title | Effective | Posted |
---|---|---|---|
– | Reliability | 1 April 2022 | 22 April 2022 |
– | Network Availability | 1 April 2022 | 22 April 2022 |
– | Transit Time | 1 April 2022 | 22 April 2022 |
– | Temporary Speed Restrictions | 1 April 2022 | 22 April 2022 |
– | Track Condition | 1 April 2022 | 22 April 2022 |
– | Unit Cost | 09 May 2017 | 2017 |
Performance Indicator Reviews
In accordance with clause 8.2(b) of the undertaking, ARTC will incorporate into its annual internal audit process, a review of Performance Indicator reporting at the first opportunity following six months after ACCC acceptance of the undertaking. Following each review, a report is prepared by ARTC’s independent internal auditors which includes ARTC’s response to the findings of the review. Reports resulting from reviews carried out in accordance with ARTC’s 2007 Access Undertaking can be viewed here.
Number | Title | Effective | Posted |
---|---|---|---|
001 | 2008-09 Performance Indicator Review findings | 23 Jul 2010 | 02 Nov 2010 |
002 | 2009-10 Performance Indicator Review Findings | 07 Feb 2012 | 08 Feb 2012 |
003 | 2010-11 Performance Indicator Review Findings | 31 May 2013 | 31 May 2013 |
004 | 2011-12 & 2012-13 Performance Indicator Review Findings | 20 Apr 2016 | 01 Dec 2017 |
005 | 2013-14 & 2014-15 Performance Indicator Review Findings | 09 May 2017 | 01 Dec 2017 |