Performance Indicator Reporting

ARTC has committed to publishing the following Performance Indicators in line with the undertaking:

Number Title Effective Posted
Reliability 1 Jan 2024 19 Jan 2024
Network Availability 1 Jan 2024 19 Jan 2024
Transit Time 1 Jan 2024 19 Jan 2024
Temporary Speed Restrictions 1 Jan 2024 19 Jan 2024
Track Condition 1 Jan 2024 19 Jan 2024
Unit Cost 20 Mar 2024

Performance Indicator Reviews

In accordance with clause 8.2(b) of the undertaking, ARTC will incorporate into its annual internal audit process, a review of Performance Indicator reporting at the first opportunity following six months after ACCC acceptance of the undertaking. Following each review, a report is prepared by ARTC’s independent internal auditors which includes ARTC’s response to the findings of the review. Reports resulting from reviews carried out in accordance with ARTC’s 2007 Access Undertaking can be viewed here.

Number Title Effective Posted
001 2008-09 Performance Indicator Review findings 23 Jul 2010 02 Nov 2010
002 2009-10 Performance Indicator Review Findings 07 Feb 2012 08 Feb 2012
003 2010-11 Performance Indicator Review Findings 31 May 2013 31 May 2013
004 2011-12 & 2012-13 Performance Indicator Review Findings 20 Apr 2016 01 Dec 2017
005 2013-14 & 2014-15 Performance Indicator Review Findings 09 May 2017 01 Dec 2017
006 2015-16 & 2016-17 Performance Indicator Review Findings 23 May 2019 20 Mar 2024
007 2017-18 & 2018-19 Performance Indicator Review Findings 10 June 2020 20 Mar 2024
008 2019-20 & 2020-21 Performance Indicator Review Findings 14 June 2022 20 Mar 2024
009 2021-22 & 2022-23 Performance Indicator Review Findings 1 Oct 2023 21 Mar 2024

Go to top