Hunter Valley maintenance shutdown

2017-11-20 @ 4:30 am - 2017-11-24 @ 9:00 am

The Hunter Valley network will undergo major maintenance works which will force a staged shutdown of the network. Work will take place within the rail corridor from:

Kooragang / Warrabrook to Muswellbrook
0430 Monday to 0900 Friday
100.5 hours

Muswellbrook to Ulan
Muswellbrook to Werris Creek
0430 Monday to 0900 Friday
100.5 hours

Werris Creek to Narrabri
0430 Monday to 0900 Friday
100.5 hours

The scheduled activity will include full track reconstruction, new rail, level crossing improvements, ballast cleaning, rail corridor tidy-up work and signalling maintenance.

Overall 100 projects will be delivered across the Hunter Valley, and the work is critical to the safety and reliability of the rail network.

Please note: times displayed are general and will vary by project.