Spotlight on… North East Rail Line (VIC)

We’ve completed main track works on our North East Rail Line upgrade in north-east Victoria, which will help ensure a smoother ride for passengers and fewer delays between Albury-Wodonga and Melbourne.

Delivering the works ahead of schedule and above the original scope, here’s what we’ve done:

  • 532km of track upgraded (and track tamping)
  • 557,000 tonnes of ballast dropped
  • 28km of mudhole removal
  • 532km of drainage reinstated
  • 85 level crossing renewals
  • 142 rail bridge upgrades
  • 173 local supplier businesses
  • $70 million injected into regional Victorian economy

We’re now focusing on signalling works, which will continue throughout the year. Learn more.

 

 